Formula 2.158
Number of sacks of lead cement required for annulus
Input(s)
$\mathrm{L}_{\mathrm{c}}$: Feet to be Cemented (ft)
$\mathrm{C}_{\mathrm{a}}$: Annular Capacity $\left(\mathrm{ft}^{3} / \mathrm{ft}\right)$
E: Excess Volume (fraction)
Y: Slurry Yield of Lead Cement $\left(\mathrm{ft}^{3} /\right.$ stroke $)$
Output(s)
$\mathrm{N}_{\mathrm{s}}$: Sacks Required (unitless)
Formula(s)
$$ \mathrm{N}_{\mathrm{s}}=\frac{\mathrm{L}_{\mathrm{c}} * \mathrm{C}_{\mathrm{a}} * \mathrm{E}}{\mathrm{Y}} $$
Reference(s)
Lapeyrouse, N. J., 2002, Formulas and Calculations for Drilling, Production and Workover, Second Edition, Gulf Professional Publishing, Page: 54.